Bid Documents
All bids have been rejected.
The District intends to reject all bids on 9/23/2020 and re-bid this project.
- Bid Results – Bid 632 RMHS Bleachers & PHS Lighting
- Venco Electric Bid Response Bid Form & Proposal for Bid No 632 – Pacifica High School Stadium Lights Only
- Nazerian Group Bid Response Bid 632 RMHS_PHS –
- Byrom Davey Bid No. 632 Rio Mesa High School Bleachers, Pacifica High School Stadium Lights
- Ardalan Bid Response Bid 632 RMHS Bleachers PHS Lighting
- Fast-Track Bid Package – Bid 632 G2K bid for Bid # 632 RMHS Bleachers and PHS Lights
- Menemsha Bid number 632 RMHS Stadium Bleachers PHS Stadium Lights
- Pars Arvin Construction Bid Response Bid 632 Rio Mesa HS and Pacifica HS
- SBS Corp Bid Response Bid 632 RMHS Stadium Bleachers Bid Docs
- WCI Proposal for Bid 632 Rio Mesa HS Stadium Bleachers & Pacifica HS Stadium Lights
- Addendum 4 for Bid 632 PHS INC2
- Addendum 3 for Bid 632 PHS INC2
- Addendum 2 for Bid 632 RMHS Bleachers
- Addendum 2 for Bid 632 PHS Lighting
- Sign In Sheet Job Walk for Bid 632 RMHS Bleachers PHS Lights 8.24.2020
- Business Cards from Job Walk Bid 632 RMHS Bleachers PHS Lights 8.24.2020
- 03-120009_INC 02 _SPC_A_PHS
- 03-120009_INC 02_DWG_A_PHS
- ADDENDUM 0_PHS INC 2
- ADDENDUM 1_PHS INC2
- 03-120515_DWG_RMHS
- 03-120515_SPC_RMHS
- ADDENDUM 1_RMHS Bleachers
- Geotechnical Report_RMHS
- Rio Mesa HS 03-CGS4332_Approval Letter
- Bid 632 RMHS Stadium Bleachers & PHS Stadium Lights
- Notice to Bidders Bid 632 RMHS Stadium Bleachers & PHS Stadium Lights
Are these 2 separate bid packages, and if so, what is the engineer’s estimate for each?
One bid package for work at both sites.Architect’s Estimate:PHS $531,011.00RMHS $2,058,000(revised answer 8/24/2020)
Rio Mesa HS notes Simplex as the Fire Alarm manufacturer, whereas Pacifica HS notes Silent Knight. Can you please confirm if this is correct, and if not, which is the appropriate manufacturer?
For Pacifica HS: Per Addendum 0 (scope of work clarification); the Fire Alarm is NOT part of the contract for this bid.
For Rio Mesa HS; per spec section 28 46 00, the contractor shall verify and match the existing manufacture.
Section 27 10 00 covers the scope of work relative to data/telecommunication/Av system cabling for Press Box at Rio Mesa Bleachers.
For the above referenced project, should we submit 1 or 2 bid bonds with our bid package?
A bid bond is required PER SCHOOL SITE. So yes, if you are bidding on both sites, 2 bonds should be submitted (in hard copy by bid due date and time).
Correct. For PHS there is no signage.
The doors and windows are a part of the Pre-Engineered Bleacher & Press-box package.
See Addendum 0 for the Scope of Work for this Bid.
The basis of award is on the lowest responsive bidder per school site.
Do you intend to split the bid and award to two different contractors?
I believe, as does our Architect, that my previous response was clear. What part do you believe is not clear? The District is making two separate awards.
Bid Bond and Bid Security are basically the same thing. The Bid Bond is the document taken and notarized (per the requirements in the bid docs) and Bid Security could be in cashier’s check or
certified check. Each serves the same purpose, to ensure bidder will enter into a contract if awarded.